PR-2026-0025
3 items, 1,620 pcs, 2.006 CBM, needed by 6 Dec 2026 — 128 days away.
The ask
Supplier terms come from the supplier record
Supplier
Lead time
145 days
Payment terms
30% advance, 70% against BL copy
Needed by
6 Dec 2026
Source
Raised by hand
Linked sales order
None — this is for stock
Items and quantities
Locked once the requisition leaves draft
| Item | Quantity (pcs) | Cartons | CBM | Available | On order | Reorder point | Remarks |
|---|---|---|---|---|---|---|---|
| SAN-1043 — Grohe Urinal 63mm | 780 | 39.0 | 0.969 | 2,510 | 1,480 | 265 | Run rate rising since March |
| PLB-1012 — Peglar Pressure reducing valve 50mm | 160 | 16.0 | 0.362 | 1,195 | 520 | 555 | — |
| PLB-1021 — Hongtai Angle valve 110mm | 680 | 34.0 | 0.675 | 3,463 | 0 | 463 | — |
3 lines · 1,620 pcs · 2.006 CBM
Decision trail
Who decided, when, and on what grounds
No decision yet
Once the requisition is submitted, the owner's approval or rejection is recorded here with the reason given.