PR-2026-0026
2 items, 1,044 pcs, 1.988 CBM, needed by 28 Dec 2026 — 150 days away.
The ask
Supplier terms come from the supplier record
Supplier
Lead time
132 days
Payment terms
30% advance, 70% against BL copy
Needed by
28 Dec 2026
Source
Raised by hand
Linked sales order
None — this is for stock
Items and quantities
Locked once the requisition leaves draft
| Item | Quantity (pcs) | Cartons | CBM | Available | On order | Reorder point | Remarks |
|---|---|---|---|---|---|---|---|
| PLB-1010 — Yuhuan Pressure reducing valve 32mm | 420 | 21.0 | 0.312 | 3,562 | 0 | 814 | Run rate rising since March |
| FIT-1070 — Yuhuan End cap 75mm | 624 | 26.0 | 1.676 | 4,420 | 3,840 | 677 | — |
2 lines · 1,044 pcs · 1.988 CBM
Decision trail
Who decided, when, and on what grounds
No decision yet
Once the requisition is submitted, the owner's approval or rejection is recorded here with the reason given.