Edit purchase order
Supplier and terms
Chosen from the supplier record, and overtypeable line by line
Taken from the FX master. Fix it on the order if the bank gave a different rate.
What the supplier wants before production starts.
Wenzhou Tianyu Faucets quotes 138 days door to door.
The UK houses are ordered once each January and drawn down through the year (PU-04).
Lines
Pieces and cartons together, with the cubic metres each line adds
| Item | Pieces | Cartons | Unit cost (USD) | CBM | Line value (USD) | |
|---|---|---|---|---|---|---|
| 0.788 | 30,040.92 | |||||
| 6.984 | 39,582.50 | |||||
| 10.595 | 63,941.64 | |||||
| 4.555 | 273,371.50 | |||||
| 2.601 | 120,110.40 | |||||
| 0.731 | 22,475.88 | |||||
| 4.383 | 278,394.24 | |||||
| 2.763 | 58,911.00 | |||||
| 1.179 | 79,447.50 | |||||
| 7.704 | 694,190.00 | |||||
| Total | 31,443 | 42.282 | 1,660,465.58 |
10 lines · $1,660,465.58 · AED 6,098,059.84 at 3.6725
Against the container
A planning aid on this form — the container itself is recorded on the shipment
Volume42.282 of 76.4 CBM · 55.3%
Weight22,310 of 26,460 kg · 84.3%
Weight is the binding constraint on this order. Open the load builder to work the fill up line by line.